Case Study

Water Treatment FacilityConcrete Storage Tank & CMU Pump House

Scope

Concrete Tank & CMU Pump House

Type

Infrastructure / Water Treatment

Contractor

Pelican General Construction

Back to All Projects

Project Overview

Pelican General Construction served as general contractor on a ground-up water treatment facility in Eastern Washington, delivering both the structural concrete storage tank and the concrete masonry unit pump house from foundation to finish, including site work.

Water treatment infrastructure is not commercial construction with a different label on it. The structures hold water permanently, they are inspected against public-health standards rather than occupancy codes, and the concrete work has to be right the first time because there is no cosmetic remedy for a tank that seeps.

Project Type Water Treatment Infrastructure
Work Performed Concrete Storage Tank, CMU Pump House, Site Work
Contractor Pelican General Construction
License #PELICGC750MJ
Region Eastern Washington
Status Completed

Slip-formed concrete: why the tank was the hard part

The storage tank was built using slip-form concrete — a continuous-pour method where the formwork rises steadily as the concrete cures behind it, producing a cylindrical wall with no horizontal cold joints.

The reason it matters on a water structure: every cold joint is a potential seep path. A conventionally formed tank poured in lifts has a joint at every lift line. A slip-formed wall does not.

The reason it is demanding: once a slip-form pour starts, it does not stop. Concrete delivery, placement rate, rebar placement ahead of the rising form, and the cure rate behind it all have to stay in balance for the duration of the pour. A delayed truck is not an inconvenience; it is a cold joint in a structure specifically built to avoid them.

That is a coordination problem before it is a concrete problem, and coordination is the general contractor's job.

The CMU pump house

The pump house was built in concrete masonry unit — block construction, chosen for this application because it stands up to constant humidity, resists the corrosion that treatment chemicals accelerate, and needs almost nothing over its service life.

It is the part of the facility with mechanical, electrical and control systems inside it, so the structure and the trades have to be sequenced against each other rather than stacked in series.

What Pelican handled

One contractor accountable end to end, which on infrastructure work is the difference between a schedule and a sequence of arguments.

Why this project is worth showing

Most commercial general contractors in the Tri-Cities have not slip-formed a water containment structure. It is a narrow skill, it is unforgiving, and the work either holds water or it does not.

If your project involves structural concrete, public infrastructure, or anything where the inspection regime is stricter than standard commercial occupancy — in Richland or anywhere across the Tri-Cities — this is the relevant reference.